2no bespoke Bus Bar Installation
Value: £105k
Client: Morgan Thermal Ceramics Project Type: Industrial Location: Bromborough, Wirral Duration: 20 Weeks OnsiteOverview
Morgan Advanced Materials are a global leader in the delivery of advanced solutions which help safeguard the worlds natural resources.
Morgan commissioned us to install 1 new, bespoke Bus Bar system due to an issue they were experiencing with poor harmonics in the existing installation.
The Solution
In busbar systems, harmonic mitigation involves minimising unwanted harmonic currents & voltages caused by non-linear loads, using methods like passive or active filters, network reconfiguration, & load balancing to ensure stable and efficient power distribution.
Mitigation Through Design
The new, intelligently designed system helped to:
- Reduce Impedance – less voltage drop & less heat generation, which can be exacerbated by harmonics.
- Effective Installation -ensuring proper grounding and earthing helps prevent harmonic currents from circulating in unintended paths.
- Preventing Degradation – the new system will withstand harmonic currents without overheating or premature failure